Pass your actual test at first attempt with PECB ISO-21502-Lead-Project-Manager training material
Updated: Aug 13, 2026
No. of Questions: 83 Questions & Answers with Testing Engine
Download Limit: Unlimited
Exam-Killer ISO-21502-Lead-Project-Manager updated and latest training material covers the main exam objectives of the actual test, which can ensure you pass easily. Free update for one year of ISO-21502-Lead-Project-Manager training material is available after purchase. Besides, our ISO-21502-Lead-Project-Manager test engine can simulate the actual test environment for better preparation.
Exam-Killer has an unprecedented 99.6% first time pass rate among our customers.
We're so confident of our products that we provide no hassle product exchange.
| Certification Vendor: | PECB |
| Exam Name: | PECB Certified ISO 21502 Lead Project Manager Exam |
| Exam Number: | ISO-21502-Lead-Project-Manager |
| Real Exam Qty: | 80 |
| Available Languages: | English, French, Spanish, Portuguese, Polish |
| Certificate Validity Period: | 3 years |
| Exam Duration: | 180 minutes |
| Exam Price: | $500 USD |
| Exam Format: | Multiple Choice, Open Book, Computer-Based, Proctored |
| Passing Score: | 70% |
| Related Certifications: | PECB Certified ISO 21502 Provisional Project Manager PECB Certified ISO 21502 Project Manager PECB Certified ISO 21502 Senior Lead Project Manager |
| Recommended Training: | PECB ISO 21502 Lead Project Manager Training |
| Exam Registration: | PECB Official Exam Registration |
| Sample Questions: | PECB ISO-21502-Lead-Project-Manager Sample Questions |
| Exam Way: | Online Proctored or Onsite at PECB Authorized Test Centers |
| Pre Condition: | Basic understanding of project management concepts; recommended completion of official PECB ISO 21502 Lead Project Manager training course; no mandatory prior exam required for entry |
| Official Syllabus URL: | https://pecb.com/en/education-and-certification-for-individuals/iso-21502/iso-21502-lead-project-manager |
| Section | Weight | Objectives |
|---|---|---|
| Individual Management Practices for a Project | 36.25% | - Directing and Executing Work - Planning and Estimating Activities - Initiating and Starting a Project - Closing and Evaluating the Project - Monitoring and Controlling Performance |
| Fundamental Principles and Concepts of Project Management | 28.75% | - Project Governance and Stakeholders - Project, Program and Portfolio Distinctions - Overview of ISO 21502 Standard - Project Management Principles - Project Life Cycle and Phases |
| Integrated Project Management Practices | 35% | - Project Organization and Roles - Project Risk and Opportunity Management - Project Communication and Reporting - Project Integration Management - Project Scope and Planning |
1. Scenario:
Leute is a low-cost airline, headquartered in Wien, Austria. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in- flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.
Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.
Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.
While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.
A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.
Question:
Allison prepared a short document in which she justified and summarized all project aspects. Which of the following did Allison create in this case?
A) Project baseline
B) Project plan
C) Project brief
2. How does ISO 21502 define project management?
A) Coordinated activities to direct and control the accomplishment of agreed objectives
B) Principles, policies, and procedures by which a project is authorized and directed to accomplish agreed objectives
C) Planned and systematic actions necessary to provide confidence to the sponsoring organization and project sponsor that a project is likely to achieve its objectives
3. Scenario:
Tricko is a clothing manufacturer headquartered in Milano, Italy. The company was founded in 2010 by Mario, a famous Italian fashion designer. Over the last few years, the company has seen immense growth and now has a chain of stores across multiple European cities. Following industry trends, the top management of Tricko concluded that the company should establish an online store. As such, they required Lily, an experienced IT engineer, to develop a brief for this potential project. After several meetings and discussions, the top management approved the project brief and assigned Lily as the project manager. For this project, she was instructed to use the guidelines of ISO 21502 on project management.
Lily initiated the project by mobilizing the project team, which included four web developers, two network engineers, and one systems analyst. In order to ensure that every team member is fully aware of their roles and responsibilities, Lily developed team performance domains which would link each project activity with the individuals responsible for undertaking it. She explained to the team members that it is important to clearly understand their roles and responsibilities, considering that the team composition cannot be reassessed or revised once the project plan is authorized to be executed. In addition, Lily defined in a document the project's contribution to the overall objectives of Tricko, which reflected the relevant project requirements and their associated acceptance criteria.
Following that, Lily worked with the project team to discuss project costs. She suggested the team initially establish cost estimates only for the first phase of the project and then for the entire project. In addition, she required cost estimates to be expressed in currency valuations and in labor hours. One of the network engineers suggested that each team member should provide an estimate, and then the team should reach an agreement for a joint estimate. On the other hand, one of the developers suggested establishing an estimate for the costs after the closure of the project, such as advertising and promotion costs. Lily agreed with their suggestions and asked them to provide a total estimate as soon as possible.
Based on the total estimate provided by the project team, Lily developed the project budget and created a list of project activities, divided them into smaller items, and assigned a budget for each item.
Question:
Based on scenario 5, which estimation method for project cost did the network engineer propose?
A) Wideband Delphi estimating
B) Single-point estimating
C) Parametric estimating
4. To whom does the project manager report?
A) Project sponsor and project board
B) Only to organization's top management
C) Key stakeholders
5. Who should be consulted as part of project management progress evaluations?
A) Project sponsors and project managers and their teams
B) Project board and project assurance
C) Work package leaders only
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: A | Question # 3 Answer: A | Question # 4 Answer: A | Question # 5 Answer: A |
Non biased QAs Converting Exams into Success
Words of praise for Exam-Killer and its truly motivated team of ISO 21502, providing exam updates in time to get their customer pass them. I bought ISO-21502-Lead-Project-Manager pdf exam
I found one of my colleagues preparing for his certification exam using Exam-Killer ISO-21502-Lead-Project-Manager testing engine. Got interested in such a handy tool and bought ISO-21502-Lead-Project-Manager real exam questions
Wanted to create a quick note to thank Exam-Killer for being so instrumental in my recently taken ISO-21502-Lead-Project-Manager exam. Exam-Killer ISO-21502-Lead-Project-Manager real exam dumps were good
Cannot Believe the Results
Struggling to pass use Exam-Killer
I was desperate to get promotion and had to pass ISO-21502-Lead-Project-Manager exam. Lack of time was the main hurdle in this goal,2 weeks before my friend told me to use it then i passed
Disclaimer Policy: The site does not guarantee the content of the comments. Because of the different time and the changes in the scope of the exam, it can produce different effect. Before you purchase the dump, please carefully read the product introduction from the page. In addition, please be advised the site will not be responsible for the content of the comments and contradictions between users.
Exam-Killer ISO-21502-Lead-Project-Manager latest torrent pdf is a great help in preparing for your actual exam that covers the latest exam objectives. All the contents of ISO-21502-Lead-Project-Manager study material are written and compiled by professional experts with the high quality and high pass rate, which can ensure you 100% pass.
Besides, we have the money back guarantee on the condition of failure. You just need to show us the failure score report and we will refund you after confirming.
Test Engine: ISO-21502-Lead-Project-Manager study test engine can be downloaded and run on your own devices. Practice the test on the interactive & simulated environment.
PDF (duplicate of the test engine): the contents are the same as the test engine, support printing.
You will receive an email attached with the ISO-21502-Lead-Project-Manager study material within 5-10 minutes, and then you can instantly download it for study. If you do not get the study material after purchase, please contact us with email immediately.
All the products are updated frequently but not on a fixed date. Our professional team pays a great attention to the exam updates and they always upgrade the content accordingly.
Yes, you will enjoy one year free update after purchase. If there is any update, our system will automatically send the updated study material to your payment email.
Once download and installed on your PC, you can practice ISO-21502-Lead-Project-Manager test questions, review your questions & answers using two different options 'practice exam' and 'virtual exam'.
Virtual Exam - test yourself with exam questions with a time limit.
Practice Exam - review exam questions one by one, see correct answers.
Online Test Engine can supports Windows / Mac / Android / iOS, etc., because it is the software based on WEB browser. You can use it on any electronic device and practice with self-paced.
Online Test Engine supports offline practice, while the precondition is that you should run it with the internet at the first time.
Self Test Engine is suitable for windows operating system, running on the Java environment, and can install on multiple computers.
PDF Version: can be read under the Adobe reader, or many other free readers, including OpenOffice, Foxit Reader and Google Docs.
We offer some discounts to our customers. There is no limit to some special discount. You can check regularly of our site to get the coupons.
Yes. We have the money back guarantee in case of failure by our products. The process of money back is very simple: you just need to show us your failure score report within 60 days from the date of purchase of the exam. We will then verify the authenticity of documents submitted and arrange the refund after receiving the email and confirmation process. The money will be back to your payment account within 7 days.
Over 67295+ Satisfied Customers